Attic wiring check before blown-in insulation
Example project
- Home
- Early-1900s house in Everett, one and a half stories
- Original request
- Insulate the attic, and keep the old wiring up there if it is safe to leave
- Found
- Two live knob-and-tube circuits along the attic timbers, one old run already cut off at both ends, and one loose splice
- Work
- Electrician’s check of every attic run, a written survey, and the written certification the state rule requires once the splice is fixed, with copies for the owners and the insulation contractor
- Timeline
- About three hours in the attic, with the written survey a few days later
- Cost
- $520
In this example, the owners of an early-1900s Everett house want blown-in insulation in the attic. The insulation contractor has seen knob-and-tube on the attic timbers and will not start until an electrician has looked at it.